CONTAINERIZED INCINERATOR FOR INCINERATING HAZARDOUS AND NON HAZARDOUS WASTES

Ø  FUEL DIESEL/NATURAL GAS; NUMBER OF PRIMARY BURNERS & RATING: 2 @ 250kw

Ø  NUMBER OF SECONDARY BURNERS & RATING: 2 @ 400kw; ELECTRICAL SUPPLY 230V 60Hz

Ø  BIN TIPPER, MONITORING SYSTEM, CLEANING SYSTEM

Ø  GAS CLEANING AND GAS MONITORING.MSW1000 General Medical Waste Incinerators burn rate up to 100kg/hr
The following should be signaling in the biding document
02. Number of laboratories    – 05

Ø  RAM LOADER CAPACITY 0.75M³; OPERATIONAL CYCLES PER DAY 8-16 Hrs.

Ø  FUEL DIESEL/NATURAL GAS; NUMBER OF PRIMARY BURNERS & RATING: 2 @ 250kw

Ø  NUMBER OF SECONDARY BURNERS & RATING: 2 @ 400kw; ELECTRICAL SUPPLY 230V 60Hz

Ø  BIN TIPPER, MONITORING SYSTEM, CLEANING SYSTEM

Ø  GAS CLEANING AND GAS MONITORING.MSW1000 General Medical Waste Incinerators burn rate up to 100kg/hr
A2400 Animal / poultry Waste Incinerators burn rate up to 200kg/hr.Laboratory  waste Management  system
01. Liqued water purification system.
02. Number of laboratories    – 05
03. The estimated liquid water waste    – 6000 L including
a. chemicals
b. toxins
c. Bio Hazardous materials.
Temporary allocated space for purifications system- 30×20
The following should be indicating in the biding document
1.Method of disposing treated waste water
2.Method of discarding the sludge
3.To follow ISO standard/regulations of Central Environment Authority[CEA]
4.Time frame for construction
5.Request the cost for each item of the project [Consultancy/designing/construction] as well for the whole project.
6.Warranty period and maintaincne.